Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2018-05-07 21:54:12

Name of Workprovinding laying sewerage work
Agency NameSh. Kuldip Singh Contractor, Chandigarh
Start Date03-10-2016
Completion Date28-02-2018
CostRs 367 Lac
JE Incharge
SDE Incharge
Engineer InchargeMs Lata Chauhan
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 60mm Interlocking Telis M35 600000.00 nos. 300000.00 nos. 300000.00 nos. Nil 100000.00 200000.00 Parveet spun pipe 100000.00