Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2019-02-17 07:08:30

Name of WorkCluster of Guruharshai , Arniwala & Abohar.
Agency NameM/s. Shapoorji Pallonji Co. Ltd
Start Date15-11-2016
Completion Date14-05-2018
CostRs 3086 Lac
JE InchargeSh. Gurwinder Singh
SDE InchargeSh. Gulshan Kumar
Engineer InchargeSh.Pritpal Singh
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 GSW Pipes 200 mm dia x 600 mm long as per IS:651 - 2007 40710 nos 7000 nos 6177 nos 0 nos 33710 nos 5000 nos Basant Vijay Industries 112 KM Mile Stone NH-15 Mahajan, Bikaner Contact Person: Mr. Vijay Saharan 9799763737 28710 nos You are requested to depute your officer for inspection please.