Column Filters
Check list for inspection of Material
Dated : 2019-02-15 05:38:34
Name of Work | Cluster of Guruharshai , Arniwala & Abohar. |
Agency Name | M/s. Shapoorji Pallonji Co. Ltd |
Start Date | 15-11-2016 |
Completion Date | 14-05-2018 |
Cost | Rs 3086 Lac |
JE Incharge | Sh. Maninder Kumar |
SDE Incharge | Sh. Ashok Kumar Maini |
Engineer Incharge | Sh.Pritpal Singh |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 400 dia Reinforced Cement Concrete Pipes, S&S type of Class NP3 (Vertical Vibrated Casting Process), 2.5 meter long ISI marked with 3mm thick HDPE Lining as per IS:458:2003 | 3493.8 mtrs | 500 mtrs | 0 mtrs | 0 mtrs | 2993.8 mtrs | 350 mtrs | M/s Anand Vertical Pipes Vill. Halim Wala, P.O Mandi Amin Ganj, Teh. & Distt. Fazilka, Punjab, India-152033 Contact Person : Mr. Jagdish M : 9878821236 | 2643.80 mtrs | You are requested to depute your officer for inspection please. |