Column Filters
Check list for inspection of Material
Dated : 2018-12-20 02:23:25
Name of Work | Cluster of Faridkot, Jaitu & Kotkapura |
Agency Name | M/s. Shapoorji Pallonji Co. Ltd |
Start Date | 16-06-2016 |
Completion Date | 15-12-2017 |
Cost | Rs 3526 Lac |
JE Incharge | Sh. Sukhjit Singh |
SDE Incharge | Sh. Gurpal Singh |
Engineer Incharge | Sh. Parul Goyal |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 150 mm & 200 mm ID RCC NP3 Pipes | 330 | NIL | NIL | NIL | 330 | 330 | M/s Indo Spun Pipes. | NIL | You are requested to depute your officer for inspection please. |