Name of Work | Cluster of Bathinda Town |
Agency Name | M/s Triveni Engineering & Industries Pvt. Ltd |
Start Date | 18-06-2015 |
Completion Date | 17-12-2017 |
Cost | Rs 21197 Lac |
JE Incharge | Sh. Rajinder Singh |
SDE Incharge | Sh. Rakesh Kumar Mehta |
Engineer Incharge | Sh. Ashwani Kumar |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | QAP of PLC System & Tubular Fine Bubble Air Diffusers for, 4.5 MLD STP | as per letter attached | 0 | 0 | 0 | 0 | as per letter attached | Quality Assurance Plan | 0 | pls approve |