Column Filters
Check list for inspection of Material
Dated : 2018-09-22 19:02:17
Name of Work | providing and laying SW PIPE sewer and construction of MPS at lalru under urban mission project |
Agency Name | M/s Oberoi Contruction Corporation |
Start Date | 06-05-2016 |
Completion Date | 05-11-2016 |
Cost | Rs 454 Lac |
JE Incharge | Sh. Gurpreet Singh |
SDE Incharge | Sh. Hari Krishan Sharma |
Engineer Incharge | Ms Lata Chauhan |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | S.W. Pipes 100 mm | 9650 | 4270 | 4270 | 0 | 5380 | 4063 | Moli Ceramics Pvt Ltd | 1317 | ||
2 | S.W. Pipes 200 mm | 14297 | 10892 | 10892 | 0 | 3405 | 3048 | Moli Ceramics Pvt Ltd | 357 | ||
3 | S.W. Pipes 250 mm | 5042 | 3726 | 3726 | 0 | 1316 | 116 | Moli Ceramics Pvt Ltd | 357 |