Check list for inspection of Material
Dated : 2018-05-02 07:25:43
Name of Work | Const. of MPS & Rising Main |
Agency Name | M/s Jai Maa Engineers & Contractors |
Start Date | 27-05-2016 |
Completion Date | 31-03-2018 |
Cost | Rs 213 Lac |
JE Incharge | Sh. Sandeep Sharma |
SDE Incharge | Sh. Deepak Kumar |
Engineer Incharge | Sh. Jitin Vasudeva |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Non clog horizontal pumps | 3 | 0 | 0 | 0 | 3 | 2 | Kirloskar | 1 |