Column Filters
Check list for inspection of Material
Dated : 2018-08-02 16:29:25
Name of Work | Const. of STP |
Agency Name | M/s Anand Associates, Chandigarh |
Start Date | 25-11-2016 |
Completion Date | 30-08-2018 |
Cost | Rs 640 Lac |
JE Incharge | Sh. Pardeep Kumar |
SDE Incharge | Sh. Tarun Gupta |
Engineer Incharge | Sh. Rahul Kaushal |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Chlorination System | 1 | 0 | 0 | 0 | 1 | 1 | Industrial Devices & ISGEC | 0 | Request for the At Site inspection of the Chlorination System |