Check list for inspection of Material
Dated : 2018-05-02 06:52:00
Name of Work | Provindg laying water supply works |
Agency Name | M/s R.G. Industries, Jalandhar |
Start Date | 08-12-2016 |
Completion Date | 31-03-2018 |
Cost | Rs 505 Lac |
JE Incharge | Sh. Kuljeet Singh Bains |
SDE Incharge | Sh. Balraj Singh |
Engineer Incharge | Sh. Jitin Vasudeva |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | D.I. PIPE 150mm 1000m | 1949 m | 0 m | 0 m | 0 m | 1949 m | 1000 m | JINDAL MAKE | 949 m | ||
2 | INTERLOCKING TILES 50,000 NO. | 2923.50 SQM | 0 | 0 | 0 | 1572 SQM | 1350 SQM | ARMANI MAKE | 1573.5 SQM |