Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2018-07-17 12:29:43

Name of WorkCluster of Guruharshai , Arniwala & Abohar.
Agency NameM/s. Shapoorji Pallonji Co. Ltd
Start Date15-11-2016
Completion Date14-05-2018
CostRs 3086 Lac
JE InchargeSh. Gurwinder Singh
SDE InchargeSh. Gulshan Kumar
Engineer InchargeSh.Pritpal Singh
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 RCC Heavy Duty (HD) manhole cover and frame of 560 mm opening, ISI marked as per IS:12592-2002 complete in all respect 1406 Nos 200 Nos 130 Nos 0 Nos 1206 Nos 200 Nos M/s Amrik Sanitary Works, Near Gurudwara, Vill. Virk Khera, Malout, Muktsar-152107. Contact Person : Mr. Amrik Singh Contact No.: +91-9463384986 1006 Nos We request you to kindly appoint your representative for the factory inspection of said materials.
2 RCC Extra Heavy Duty (EHD) manhole cover and frame of 560 mm opening, ISI marked as per IS:12592-2002 complete in all respect 100 Nos NIL NIL 0 Nos NIL 100 Nos M/s Amrik Sanitary Works, Near Gurudwara, Vill. Virk Khera, Malout, Muktsar-152107. Contact Person : Mr. Amrik Singh Contact No.: +91-9463384986 NIL We request you to kindly appoint your representative for the factory inspection of said materials.
3 Orange colour safety footrest of minimum 6mm thick plastic encapsulated as per IS: 10910 on 12mm dia steel bar confirming to IS: 1786, complete in all respect. 9711 Nos 2000 NOS 1000 Nos 0 Nos 7711 Nos 1000 Nos M/s Amrik Sanitary Works, Near Gurudwara, Vill. Virk Khera, Malout, Muktsar-152107. Contact Person : Mr. Amrik Singh Contact No.: +91-9463384986 6711 Nos We request you to kindly appoint your representative for the factory inspection of said materials.