Column Filters
Check list for inspection of Material
Dated : 2018-07-13 17:57:35
Name of Work | Cluster of Bassi Pathana & Sirhind |
Agency Name | Gannon Drunkenly (GDCL) |
Start Date | 17-06-2016 |
Completion Date | 16-12-2017 |
Cost | Rs 9758 Lac |
JE Incharge | Inderjit Singh |
SDE Incharge | Sh. Lalit Mittal |
Engineer Incharge | Sh. Sabjit Singh |
Sr.No | Description of Material | As per approved scope of agreement | Already Inspected | Already received at site | In Transit | Balance as per approved scope of agreement | Now offered for Inspection | Make | Balance | Remarks | |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Inspection of 200mm,400mm dia SW pipe | 200mm dia 117158No.400mm dia 6480No. | 58100 No. & 4610 No. | 38300 | 2000 | 59058 | 5000 | Sorkhi Industries Pvt.Ltd. | 54058 | Dear Sir, Kindly arrange to depute inspecting officer for above said materials. |