Inspection Report

Column Filters

Check list for inspection of Material

Dated : 2018-07-11 14:47:20

Name of WorkBoring & installing Tubewells ( Under AMRUT)
Agency NameM/S Dhruv Tubewell Engineers
Start Date27-04-2017
Completion Date26-10-2017
CostRs 138 Lac
JE InchargeSh. Gurwinder Singh
SDE InchargeSh. Gulshan Kumar
Engineer InchargeSh.Pritpal Singh
Sr.No Description of Material As per approved scope of agreement Already Inspected Already received at site In Transit Balance as per approved scope of agreement Now offered for Inspection Make Balance Remarks
1 Submersible Pump 55 mtr. Head 4 nos. 0 0 0 0 4 SU pumps 0
2 Submersible Pump 75 mtr. Head 6 nos. 4 4 0 2 2 SU pumps 0