Bathinda |
|
|
|
Balance work will be done after construction of duct by irrigation deptt. Work yet to be done by irrigation deptt. Crossing of railway line work allotted by railway but yet to be started |
|
|
03-05-2021 |
|
|
Amritsar(MC) |
|
|
|
Whole sewerage network in South Zone area had been commission since more than one year. But MC Amritsar is not taking over this sewer. Continued correspondence is being made with MC Asr but still no action has been taken by them. There is huge problem of Maintenance as local public representative put pressure on our department to do regular maintenance which is prerogative of MC Asr. Furthermore, there is no provision for maintenance in JICA project. Now estimate for O&M has been sent to MC Asr for providing funds for O&M already done. Urgent intervention is required from higher level |
The undersigned had joint meetings with all EEs/SE of MCA and TA to CM. CEO Sir also intervened and had talk with Commissioner MCA. Continuous daily efforts are being made by myself/EE/SDE/JE. In spite of all these, the MCA officers/officials are willfully delaying the process. Only 13 km sewer in south has just been checked by MCA JEs but that too not yet taken over. During this month only four km sewer in North Zone has been taken over making total as 5 km. Suitable immediate action is urgently required. |
Meetings already held with Municipal Commissioner, MC, asr and SE , MC amritsar but still they have taken only 4.5 km sewer. Worthy CEO requested to Commissioner, MC Asr. Again I contacted commissioner MC and she directed to SE , O |
29-11-2018 |
|
|
Barnala |
AMRUT |
|
|
Design Statement for Main Sewer is yet to be submitted by agency. |
|
|
22-09-2018 |
|
|
Goraya |
URBAN MISSION |
|
|
The NOC for laying the rising main along Goraya distributory is pending from Drainage division, Jalandhar. Despite of various efforts, the NOC could not be obtained. |
|
|
29-08-2018 |
|
|
Phagwara |
URBAN MISSION |
|
|
Permssion for crossing of water supply line at 14 No. sites under Mathura- jalandhar petroleum pipeline at phagwara town. B.T. amounting to Rs. 52.15 Lacs deposited. NOC obtained on dated 22.06.2018. |
|
|
29-08-2018 |
|
|
Jandialaguru |
URBAN MISSION |
|
|
Work started by the agency, Rig shifted near old bus stand and drilling will be started soon.
Agency has been directed to expedite the progress of work. |
|
|
27-08-2018 |
|
|
Ajnala |
URBAN MISSION |
|
|
MC authorities and local representatives are amended to first lay the sew. in very narrow streets where W/S lines already exists.
These streets has personally visited on the basis of which it can be said that laying of sewer in these streets is not feasible. the work as thus temp. halted. |
EE/SDE are directed to sort out the issue and fix my meeting with the local MLA to sort out the issue, if my intervention is required. Action be taken and completed in one week and convey the outcome personally. |
|
27-08-2018 |
|
|
Ahmedgarh |
URBAN MISSION |
|
|
Villager has stopped the laying of Rising Main and this matter has been taken up with district administration. |
|
|
24-07-2018 |
|
|
Phillaur |
NRCP |
|
|
The STP is under stabilization. |
No comments required |
|
20-06-2018 |
|
|
Kapurthala |
URBAN MISSION |
|
|
Vent shafts are to installed. Inspection done, material yet to be received at site. |
|
|
20-06-2018 |
|
|
Tarn Taran |
URBAN MISSION |
|
|
Agency restarted the work.
Now there is no issue |
no comments required |
|
20-06-2018 |
|
|
Nakodar |
URBAN MISSION |
|
|
Estimate amounting rs. 80.00 Lac and is under vetting stage |
|
|
23-05-2018 |
|
|
Khanna |
AMRUT |
|
|
Existing. |
NO ISSUE. |
|
17-05-2018 |
|
|
Ramdass |
URBAN MISSION |
|
|
100% work completed. There
Is no issue |
No comments required |
|
17-04-2018 |
|
|
Raja Sansi |
URBAN MISSION |
|
|
100% work completed. There
Is no issue |
No comments required |
|
17-04-2018 |
|
|
Bariwala
|
URBAN MISSION |
|
|
Sanction for intake of Raw water from Sirhind feeder is in progress. |
|
The case for sanction of intake has been submitted to SE canal Div Ferozpur (Sirhind Feeder) for approval. EE pwssb Has been directed to pursue the case at its logical end |
17-04-2018 |
|
|