Town Name | Program | Issue Type | Issue Name | Issue Details | SE Comment | CE Comment | Date | Action | Action |
---|---|---|---|---|---|---|---|---|---|
Abohar | Work started | 15-06-2021 | |||||||
Sirhind | URBAN MISSION | Case for permission has been sent to Project Director NHAI PIU Ambala for crossing of National Highway Road Near Railway road during July 2016. Case recommended for approval by consultant to PD, NHAI vide letter dated 27.06.2018. Case forwarded to Highway Administration, Regional Office, MoRTH, Chandigarh vide PD office letter no. 1951 dated 06.08.2018 for final approval. Case uploaded online by Regional Office, MoRTH, Chandigarh for public objections. Case returned to PD office for amendment in case as per new MoRTH guidelines by Regional office. Case uploaded in public domain for 30 days for any objection. No objection received, case sent to PD office for final deposit of funds. Funds being deposited as Bank Guarantee. | 19-09-2019 | ||||||
Moga | URBAN MISSION | MAIN SEWER NISHANS ARE NOT CLEAR FROM | 10-07-2019 | ||||||
Sangrur | URBAN MISSION | Land for STP Zone-I not available.Advertisement was given by MC Sangrur in newspaper. 2 no applications received and feasibility report submitted to MC Sangrur. | 20-05-2019 | ||||||
Faridkot | URBAN MISSION | PAYMENT MADE TO NH. WORK COMPLETED. | The Issue may please be dropped . | 28-11-2018 | |||||
Badhni Kalan | URBAN MISSION | Scheme is to be dropped. as LAND for MPS const is still not handed over by NAC | 02-10-2018 | ||||||
Phagwara | URBAN MISSION | Permission applied for laying the water supply line along Phagwara Ropar NH-344 A at phagwara town. Due to non avaiaalbility of ROW of NH, joint inspection with the officals of the national highway was conducted on dated 30.05.2018. The possibility of laying the water supply was explored and it was observed that the water supply line can be crossed though the culverts due to non availability of ROW near the bridge sites. Now it has been decided to cross the water supply line at one of the crossings in front of Guru nanak nagar for providing water supply facility to this area and rest of the water supply line along NH can be laid in the future when there will be increase in poulpation of the area along NH. | 29-08-2018 | ||||||
Barnala | AMRUT | Yes, the case to lay down the sewer from Khuddi chowk to STP/MPS site not granted by National Highway till date. | Another parallel case applied to Forest Deptt for laying sewer lines in kutcha portion along this road already sent for In Principal approval to MOEF, GOI by Nodal Officer (FCA). | s | 17-04-2018 |