Abohar |
|
|
|
NA |
|
|
15-06-2021 |
|
|
Amloh |
URBAN MISSION |
|
|
Land for construction of STP (3MLD) has been identified in Bhadal Thuha Village. The area of land is 1.0 Acre. Price has been fixed by committee under the chairmanship of D.C. Fatehgarh Sahib @ Rs. 40.40 Lacs per acre. Case has been sent to DDLG Ludhiana by EO MC Amloh for sending the same to DLG office Punjab and same has been forwarded by DDLG Ludhiana to DLG office on 12.06.2018 for final approval. Case received back with observation and resubmitted to DLG office for approval. |
|
|
12-09-2019 |
|
|
Kharar |
URBAN MISSION |
|
|
Site for IPS provided by MC, Kharar but work withheld due to litigation of farmers for approach road to their fields, stay by lower court for construction. Application moved by MC, Kharar for vacation of stay. Case dismissed with partial orders in favour of MC Kharar but work cannot be executed. Application moved in higher court for revision in orders. Bill finalised in consultation with MC and new tenders will be floated after finalization of land. |
|
|
09-08-2019 |
|
|
Faridkot |
URBAN MISSION |
|
|
Price fixation committee approval sent to PSLG sir vide DC letter no 192 dated 29.06.19 for STP. A separate case for social impact assessment is in process for compulsory aquisition of road to marked land. |
|
|
10-07-2019 |
|
|
Kot Ise Khan |
URBAN MISSION |
|
|
Still OHSR Land is not handed over by M.C. Scheme is to be dropped after approval from H.O . All the laid lines are commissioned through old Tubewells. |
|
The E.E is directed to have a meeting with M.C regarding land issue . If the M.C is not interested in providing land for Const. of OHSR prepare the case for dropping of this scheme . |
10-07-2019 |
|
|
Badhni Kalan |
URBAN MISSION |
|
|
NAGAR PANCHAYAT DID NOT HANDED OVER LAND FOR CONSTRUCTION OF MPS. HENCE CONTRACT HAS BEEN CLOSED |
|
|
10-07-2019 |
|
|
Dhuri |
URBAN MISSION |
|
|
Land for 6 MLD STP yet not available. A meeting has been fixed by local MLA with Panchayat of Daulatpur for transfer land. |
|
|
06-07-2019 |
|
|
Sangrur |
URBAN MISSION |
|
|
Land for 11 MLD STP yet not available. M.C Sangrur has called a meeting for discussion of rates on dated 11.07.2019. |
|
|
06-07-2019 |
|
|
Kapurthala |
PIDB |
|
|
The dispute of IPS site at sheikhupura basti has been resolved during the joint meeting held with PA to MLA kapurthala, president of the mata temple in the area, Area councillor and other persons of the area. The Municipal councillor of the area has been given his consent to start the work at site and assured the department that no dispute will occur in the future during the currency of the work. |
|
|
29-08-2018 |
|
|
Goraya |
URBAN MISSION |
|
|
The site of STP was jointly visited with worthy SE(J) alongwith EO goraya. EO was asked to provide alternate MC land nearby for construction of STP as the existing STP site is a pond which is very deep i.e nearly 20 feet and continously rain/sewage water is reaching the pond site. So pond will never be empty and as such construction of STP is not possible. EO was also requested to acquire the land by negotation if alternate MC land is not available nearby. |
|
|
29-08-2018 |
|
|
Phagwara |
URBAN MISSION |
|
|
One no. site for 0.50 lac gallon OHSR at Mohalla Green avenue & one no. site for 2.00 lac gallon OHSR at Mohalla Kaulsar are yet to be handed over by MC PHAGWARA. |
|
|
24-07-2018 |
|
|
Mehatpur |
URBAN MISSION |
|
|
Site handed over by MC, OHSR Construction is in progress. |
|
|
24-07-2018 |
|
|
Jandialaguru |
URBAN MISSION |
|
|
Funds not tied up for
MPS / STP |
No live project as on date nor any funds are tied up as on date. The issue is recommended to be dropped from portal till funds are tied up. |
|
11-07-2018 |
|
|
Tarn Taran |
PIDB |
|
|
4 MLD STP land acquired and
Possession taken. No issue |
Land acquired for 4 MLD STP and work is progressing satisfactory .There is no issue of land now. It is recommended drop the issue from the portal. |
|
10-07-2018 |
|
|
Bathinda |
URBAN MISSION |
|
|
4.85 Acre improvement Trust land taken over by MCB and Handed over to PWSSB but improvement trust is yet to be hand over the land to the MC and 0.31 acre private land is being taken by MCB through negotiation has been handed over to PWSSB |
|
The EE has been directed to coordinate between MC and Improvement Trust Bathinda to settle this transfer of land. |
23-05-2018 |
|
|
Khem Karan |
PIDB |
|
|
5 kanal land is reqd for 2 MLD
STP at Khem Karan. As per
New act advertisement given
By EO khem karan. No application
Received. |
No funds tied up nor any land has been selected. The issue is recommended to drop till funds are tied up. |
|
22-05-2018 |
|
|
Jalandhar (MC) |
NRCP |
|
|
Dhanowali land issue. Advertisement issued by M.C.(J) to get land. 1 No. bid received . Price Fixation meeting held on 28.11.2016 and rate fixed @ 1.45 Lac per Marla. Approval received from DLG on 29.8.2017. Registry of Land done by M.C. (J). |
|
|
18-04-2018 |
|
|
Patti |
URBAN MISSION |
|
|
Sewerage work completed.
MPS/STP not alloted due to
Non availability of land |
Sewer has already been laid up to last point (very near to Kasoor drain leading to Pakisthan) without acquiring STP land. Now the owner of that land has refused to give land. It has been now planned that first the acquisition will be started and completed as per new act. If the owner offers land (may be up to 25% higher rate collector rate), necessary approval will be obtained from FD. If the owner refuses, then the process for acquition will be started. EE has been advised to have joint meeting this week with EO and start the process as above.
|
|
17-04-2018 |
|
|
Talwara |
|
|
|
Land identified by nagar Panchayat Talwara, Land of Tubewell Yet to be Handed over to this office. |
|
|
16-04-2018 |
|
|